First, the requirements before installation
Ground requirements before the installation of SPC stone plastic lock flooring: the leveling work must have been completed.
Ground flatness: 1 meter long distance slope less than 3 mm.
Flooring can be installed on existing tile floors, old wooden floors, terrazzo floors, supporting underfloor heating, cement floors, staircase floors; As long as the ground is level, it can be paved.
SPC stone plastic lock floor installation construction tools: tape measure, cutting machine, hammer, knock block, glass glue.
Second, the construction management process of SPC stone plastic lock floor installation project:
Step 1: Clean the foundation floor.
There should not be a lot of sand on the ground, so as not to affect the later use of the floor and various small problems.
Step 2: After the ground is cleared, spread moisture-proof cotton.
Cause:
1. Because the lock floor has a moisture-proof effect, the reason for laying moisture-proof cotton now is to separate the ground from the lock floor to prevent the sound of some fine sand particles on the ground that have not been cleaned, and "squeak" when walking;
2. We all know that the lock floor is thinner than the wooden floor and the composite floor, if it is directly laid on the ground because of its thinness, the effect of stepping on the tile floor when walking is hard and hard. In addition to the appearance is better, but the foot feeling is too hard, then the moisture-proof cotton can also improve the foot comfort moderation problem.
Step 3: Choose the pavement method:
1. 369 splicing method;
2, 4/5 staggered front shop;
3. I-shaped splicing;
4. DIY creative splicing;
Step 4: After choosing the paving method, start laying from the position of a right-angled wall. After aligning the buckles, such as the 45-degree angle buckle is embedded, there is no need to make a wooden frame for floor laying; It can be installed in such a way that it can be laid out directly, leaving a 10 mm gap between the wall and the board.
Step 5: After the whole ground paving is completed, it enters the latter process. If you need to install the baseboard after locking the floor, install the baseboard directly. If there is no baseboard installed, it will be directly closed with glass glue. (That is, the edge of the wall, lock the gap between the floor and the wall, and close it with glass glue, which will look more beautiful.) )